Sidehall Refurbishment:  

Thursday, 27th July - Thursday, 10th August

Name *
Name
Checkbox *

Please let us know via the form opposite, the jobs you're able to help with.
 

Screen to Balcony
Create sub-frame for artwork
Determine artwork type and design
Site artwork and fix

Low level timber work
Remove radiators and store
Strip varnish to wood work
Reseal woodwork
Box pipes
Re-site radiators

Decoration to walls

Clean down area

Re-site cupboards/chairs

Hall & Balcony Clearance
  27th & 28th July - Daytime & Evenings

Dispose of chairs
Re-site cupboards, tables to Tea Room
Take down & store Notice Board
Clear balcony

Flooring
  
27th & 28th July - Daytime & Evenings
Take up & dispose of carpet and ply sub-floor
Inspect floor and repair if possible
Sand and seal if possible
Re-ply & carpet

Ceiling
Treat dry rot
Repair hammer beam and T & G
Remove old fittings

Electrics
Tidy up existing electrics, remove unnecessary wiring
Run wiring to additional ring main
Add sockets